National Highways Authority of
India v. M/S JSC Centrodorstroy
Civil Appeal No. 2529 of 2016
Facts
The present Case involves a dispute relating to the costs involved in a Works Contract. The
Respondent was awarded the Contract on 12.03.2001 by the Appellant. The main
bone of contention was Clause 14.3 and Clause 70.8 of the COPA (Conditions of Particular
Application) which is stated hereunder:
“Clause
14.3 of “Instruction to Bidder”
All
duties, taxes and other levies payable by the Contractor under the contract, or
for any other cause, as of the date 28 days prior to the deadline for
submission of bids, shall be included in the rates and prices and the total Bid
Price submitted by the bidder.”
“Clause
70.8: Subsequent Legislation
If,
after the date 28 days prior to the closing date for submission of bids for the
Contract there are changes to any National or State Statute, Ordinance, Decree
or other Law or any regulation or by-law of any local or other duly constituted
authority or the introduction of any such State Statute, Ordinance, Decree,
Law, regulation or by-law in India or States of India which causes additional
or reduced cost to the Contractor, other than under the preceding Sub-Clauses
of this clauses in the execution of the contract, such additional or reduced
cost shall, after due consultation
with the Employer
and the Contractor,
be determined by the Engineer and shall be added to or deducted from the
Contract Price and
the Engineer shall
notify the Contractor accordingly
with a copy
to the Employer. Notwithstanding the foregoing,
such additional or reduced cost shall not be separately paid or credited if the
same shall already have been taken into account in the indexing of any inputs
to the Price Adjustment
Formulae in accordance
with the provisions of
Sub-Clauses 70.1 to 70.7 of this Clause.”
Arguments
The
disputes pertaining to the additional costs incurred were taken before the
Arbitral Tribunal. According to the Respondent, there were revisions in the
rate of Service Tax with reference to the Insurance Policy from 5% to
10.30% over a period of time. Hence the Service Tax paid in excess of 5%
was reimbursable by the Appellant under Clause 70.8 of COPA. Similarly, the Respondent
contended that in terms of the Clause 10.1 of COPA, the Respondent was required
to furnish Bank Guarantee by way of Performance Security and the Service Tax in
relation to the Bank Guarantee as collected by the Bank had risen from 5% to
10.30% during the course of the contract. Hence the Respondent was entitled to
be reimbursed by virtue of Clause 70.8 of COPA.
The
Arbitral Tribunal accepted the aforesaid claims by its Award dated 28.02.2013
and ordered the Appellant to pay such sums to the Respondent. As per the
Arbitral Tribunal, the additional costs as a result in revision of Service Tax
were covered under Clause 70.8 of COPA. It also observed that Service Tax was
not an input to the indices used in Prices Adjustment Formulae in Clause
70.3.
Proceedings
before the Supreme Court
The
Award passed was challenged under Section 34 of the Arbitration and
Conciliation Act, 1996, whereby the Single Judge dismissed the Petition by
Order dated 21.10.2013. An Appeal was preferred before the Division Bench of
the High Court. However, the Division Bench affirmed the view taken by the
Single Judge and dismissed the Appeal.
The
matter came up before the Supreme Court where it was contended that only those
claims which were constructional inputs alone would be eligible to be covered
under Clause 70 of COPA and the facility of Bank Guarantee was optional. The
Supreme Court rejected this argument and held that Bank Guarantee was a
mandatory condition under Clause 10.1 and Clause 10.2. It further held that
construction of the terms of a Contract is primarily for an Arbitrator or
Arbitral Tribunal to decide and unless the Arbitrator or Arbitral Tribunal
construes the contract in such a way that no fair minded or reasonable person
could do, no interference by Court is called for.
In the
instant case, it was observed by the Hon’ble Supreme Court that the view that
the increase in rates of Service Tax in respect of Bank Guarantee and Insurance
Premium is directly relatable to the terms of the Contract is certainly one of
the possible views. Merely because different views are possible on same subject
matter does not warrant interference by the Courts.
Opinion
I feel
that the reasoning adopted by the Supreme Court is sound as some amount of
leeway has to be given to the Private Contractors. Today the Governments are
hell bent on initiating Recovery Proceedings against the Private Contractors
for the most trivial issues and are never willing to pay back anything even
when there is a fault on part of the Government. The High Courts also adopt
different and divergent views in this respect. There is no uniformity in this
respect. It is understandable that some degree of latitude is necessary to be
given to the Government as it is the biggest litigant and has to fight each and
every case to recover its money. However, this degree of latitude cannot be at
the cost of the established legal principles or fair reasoning. The Order by
the Supreme Court will certainly act as a guiding beacon for similar cases
pending in the various High Courts.
Nice blog has been shared by you. it will be really helpful to many peoples who are all working under the technology.thank you for sharing this blog.
ReplyDeleteBlockchain technology